Lyons Avenue

Status: Complete

As part of the broader bikeway network in Near Northside, the first on-street bike lane to be implemented will be on Lyons Avenue! Construction is complete, with green paint applied at certain intersections.

Lyons Avenue bikeway serves as a piece of the Phase 1 Bikeway Network in the community, which totals 9.2 miles and includes key north-south and east-west connectors such as Hardy, Elysian, and Kelley.

The Lyons Avenue on-street bike lane will:

Extend 0.67 miles in length from Hardy Street to Jensen Drive

Maintain 6ft in width on both sides of the street

Enter into construction at the end of October 2018 (estimated) and

Complete construction at the end of December 2018 (estimated)

Connect people on bikes to major destinations, such as Saint Arnold's Brewery

Enhance bikeway connections into Downtown and Fifth Ward

Acknowledgements

Project Partnerships

Harris County Precinct 1

City of Houston Planning and Development Department

Houston Public Works

Project Management & Design Consultants

Jones Carter

Toole Design Group

Traffic Engineers, Inc (TEI)

Contact Us

For more information, please contact Houston Bikeways Program at 832-395-2700 or [email protected].